USPDECONTAMINATION AND STERILIZATION PRE, MID AND POST PROCESS-CONSIDERATIONS

Nov. 24, 2025

INTRODUCTION

The decontamination and sterilization of equipment, materials, components, and products are critical processes when utilized for microbial control. There are process control requirements associated with their execution that are vital to maintaining process reliability, aside from those directly associated with the individual process. These include actions and measures taken prior to, during, and subsequent to the process execution. Because these actions are performed in varied ways, the described practices are only broadly defined and will require adaptation to the individual circumstances.

 

PREPROCESSING ACTIVITIES

These may be conducted at any time prior to the start of the sterilization cycle.

 

Cleaning of Materials

Items to be processed must be free of residues that could interfere with the penetration of the sterilizing agent on the surfaces that are to be treated. This is of particular importance for equipment and utensils that are reusable, as the potential for the presence of soil and other residues is increased, and thus cleaning prior to reprocessing is required. In particular, the reuse of product contact tubing is not recommended because it is difficult to clean. Single-use materials should be examined before preparation for treatment. Once cleaned or inspected, items should be protected until they are wrapped or packaged in preparation for sterilization.

 

Wrapping and Container Controls

Many items to be sterilized are wrapped or placed in containers prior to processing. Flexible wrapping materials should be subject to quality standards, including material controls, porosity, and shelf life, to ensure consistency of performance and integrity during the sterilization process, and until opened. Medical devices and other items sterilized in permeable semirigid blister packaging require rigorous controls on the packaging materials, given their subsequent handling and intended longer shelf life. Rigid containers used to hold load items require inspection and cleaning prior to reuse.

 

Load Wrapping and Preparation

The wrapping of items should follow written procedures that are sufficiently detailed to ensure that it is accomplished in a consistent manner. The orientation of individual items, including tubing length, positions of valves and clamps, dimensions of the wrap, and sealing materials, should be closely defined. Where necessary, appropriate identification should be placed on the exterior of the wrapped or contained items to avoid potential mix-ups. Where appropriate, sterilization indicators should be placed on wrapped or contained items, or externally to confirm process lethality.

 

Preprocess Documentation Review

Batch records, standard operating procedures, and related documents should be reviewed and compared with the items that are to be sterilized, to confirm identity, appearance, and quantity. The appropriate entries must be made to properly document the sterilization process. Entry of information on chart recorders, control systems, and other recording devices is required to link the records with the materials to be sterilized. It must be confirmed that appropriate and sufficient charts, paper, ribbon, and/or ink are available for the documentation of results during the run. Entries of date, time, and sterilization load identification should be made in the equipment log and signed by the operator.

 

Presterilization Equipment and Room Clearance

The sterilizer chamber and the loading area should be visually checked to ensure that materials from the prior sterilizer load are no longer present. Items to be sterilized should not be introduced unless all previously processed materials have been removed.

 

Bioburden Sampling

If necessary, samples should be taken of load materials as required for bioburden monitoring. The samples should be labeled with the date, time, sterilization load identification, and operator’s name.

 

Load Placement

The individual load items must be placed and oriented into position as required by the operating instructions. The load itself should be positioned in the sterilizing chamber, and any load monitoring probes located as required.

 

MID-PROCESS ACTIVITIES

Deviation Reporting

The operator should report and record any unusual occurrences during the execution of the sterilization process, including sounds, odors, leaks, or other atypical events, and should respond as instructed to any audible or visual alarms related to the process.

 

Operator Safety

Operators must follow all safety directions, including the proper wearing of required personal protective equipment. This may also be necessary during unloading of the equipment, and transfer of the load upon completion of the sterilization cycle.

 

POST-PROCESS ACTIVITIES

Material and Load Inspection

As materials are removed from the sterilizer, they should be inspected for evidence of damage, torn wrapping and/or covers, color changes, excess condensation, and other indications that the products' integrity may have been compromised during the sterilization process.

 

Physical Indicator Recovery and Review

The operator should recover and examine all external physical indicators positioned on or in the load. Any anomalous indicator result should be immediately reported to supervisory personnel. If indicators are retained as part of the sterilization record, they should be fully accounted for and properly identified before transferring the sterilizer load.

 

Post-Process Sample Collection

If required, post-cycle samples should be taken from the designated locations within the load. Samples should be identified as they are removed, to ensure traceability as to the location in the load and the sterilizer run identification.

 

Post-Process Handling and Load Protection

The load should be handled carefully to avoid loss of wrapping/cover integrity. Where required, post-sterilization protective covers on materials should be applied in accordance with defined procedures. When post-cycle aeration is required, the load should be transferred expeditiously to minimize exposure of the sterilized items to the operator.

 

Post-Process Equipment and Room Clearance

The sterilizer chamber and the unloading area should be visually checked to ensure that all materials from prior use of the sterilizer are removed.

 

Post-Process Documentation Review

The operator should recover the sterilizer printout, recorder charts, and other relevant process information for inclusion in the sterilization cycle records.

 

GENERAL CONSIDERATIONS

Calibration

The sterilizer and its associated instrumentation must be within their calibration intervals.

 

Personnel Training

Operators and supervisors must be trained in the fundamentals of sterilization microbiology, and must adhere to instructions for sterilization.

 

CONCLUSION

The proper utilization of sterilization equipment is central to the elimination of microorganisms in a variety of settings. Personnel practices relating to sterilizer operation play an important role in ensuring the reliability of the process.▲ (USP 1-May-2023)

 

NOTE:Source from USP,The above content is for reference only. For more information, please click the original text:https://online.uspnf.com/uspnf/document/2_GUID-1BA58939-D64D-4BF0-B0B3-4EC7363CC4C8_10101_en-US?source=TOC

Related Products

Related News

  • wechat

    Ella: +86 13373342369

Chat with Us